We prep'ed the the perma Base by making sure all screws were counter sunk then we swept the surface clean. We applied Type 1 mastic to the base with a 1/4 inch V grove trowel. We set all full tiles and let dry for 24 hours. Then, using a diamond wet tile saw, we cut all the remaining pieces and set them. We will let the floor dry for 1 week then grout. Next, the shower.